| Anderson Park Community Gardens Construction |
Active City Park Projects Managed by The Construction DivisionTurf Replacement, Grass Lawn Park Softball
Field 1 Construction October 2025 $1,851,216
Redmond Central Connector Phase 3 Redmond Central Phase 1 $1,851,216 2019-2020 Complete August 2025 $8,075,000
Turf Replacement, Hartman Park Baseball
Infield Construction October 2025 $599,245 2019-2020
Reservoir Park Sports Court Replacement Construction October 2025 $1,181,682.
Meadow Park Sports Court Replacement Construction October 2025 $593,910 2019-2020
Pre-Design $599,245 2019-2020 $593,910 2019-2020
Idylwood Park Parking Lot/ Expansion and
Frontage Improvements/
SE Redmond Park $4,476,663 2025-2026 This is a joint project with Traffic Operations Pre-Design October 2028. $13,757,591 2025-2026 Project is starting earlier than planned.
Disclaimer: I did not watch this meeting on Comcast Channel 21, in-person, Facebook or streaming on the website or a study session. Some of the labeling of the construction projects may not be aligned with the dates but the dollar amounts are correct.
-- Council Public Works joint meeting with Parks, October 3, 2025