Click on a link below to jump to updates for other projects funded by the 2016 bond:
|
|
Juanita High School |
- Juanita High School students returned to campus for their first day of school on September 4. Students will attend classes in what remains of their old building, as well as in 15 double-classroom portables. The first phase of the new school building will open in one year.
- Roof installation is complete.
- Masonry at the theater is complete.
- Exterior work – including brick veneer and window installation – has begun.
- Sheetrock installation has begun.
- A regional operating engineers union strike has been resolved.
|
|
|
|
Margaret Mead Elementary School |
- Concrete floors started.
- Structural brace frame concrete footings are complete.
- Borings for geothermal wells started.
- Utility work is in progress.
- A regional operating engineers union strike has been resolved.
|
|
|
|
Peter Kirk Elementary School |
- Concrete floors started.
- Borings for geothermal wells are complete.
- Utility work is in progress.
- A regional operating engineers union strike has been resolved.
|
|
|
|
Old Redmond Schoolhouse |
- Bids for the project have been advertised.
- A pre-bid contractor site walk was held.
- Construction is expected to begin this fall.
|
|
|
|
|
| Explorer Community School
The school opened in fall 2017. Four innovative and energy-efficient modular classroom buildings replaced aging portable classrooms.
|
|
|
|
Have a question about a bond project? Let's Talk! Have a question about any of these projects? Ask us through our "Let's Talk" system. This system allows you to share comments or ask questions to members of our team.