Thursday, January 23, 2014

$850,000 Rechannelization project of 166th Avenue moves forward


Redmond City Council approved $80,600 in supplemental spending with David Evans and Associates for final design and construction services for 166th Rechannelization.  Total estimated project costs are $850,000 with completion expected by year-end.


Background:  In August 2013, David Evans and Associates was selected to provide analysis and conceptual design of the 166th Avenue NE Rechannelization project.  In a Decemeber 10, 2013 Council study session Council directed staff to move forward with the final design and construction of the baseline project.  The baseline project consists primarily of restriping the corridor to a 3-lane roadway, minor intersection modifications at NE 85th Street, and adding pedestrian beacons at NE 91st Street and NE 95th Street.  