Tuesday, September 11, 2018

Five local roads will be significantly impacted by light rail

Image result for redmond light rail videosSound Transit is extending light rail from Seattle to Redmond, with four stations in Redmond. Two stations, Overlake Village Station and the Redmond Technology Station, will open in Overlake in 2023. These stations are now under construction. Two stations will open in 2024, one in Southeast Redmond and another in Downtown Redmond.  The Downtown Redmond Link Extension is the 3.4-mile extension of light rail from the future Redmond Technology Station at NE 40th St. to the terminus station in Downtown Redmond.

Although the development agreement is not expected to be finalized until early 2019, there are two topics on which staff are seeking early Council input so that Sound Transit can provide clear direction to design-build teams proposing on the project. Those topics are: street closures during construction, and the Marymoor Village station layout.

Street Closures During Construction While most light rail construction for the Downtown extension will be along SR 520, limiting impacts to city streets, there are five areas that will be significantly impacted by construction.

The Overlake “Triplets”
1. NE 40th St. at the eastbound SR 520 ramps
2. NE 51st St. at the eastbound SR 520 ramps
3. NE 60th immediately east of SR 520 Downtown Streets

4. NE 76th St. between 164th and 170th Aves.

NE 5. 166th Ave. NE between NE 76th St. and Cleveland St.

Source:  8/28 Council Study Session memo